Time Lines
Phase 1 – Requirement Finalization, Hardware & Firmware Design (6 Weeks)
| Week | Task | Description | Deliverable (Internal) | Responsibility |
|---|---|---|---|---|
| Week 1 | Requirement Finalization | Finalize technical requirements and performance targets. | Final Requirement Document | Hardware + Firmware Team |
| Week 2 | Component Selection | Select sensor, LoRa (Mesh) SoC, PMIC, and components. | Approved BoM | Hardware Team |
| Week 3 | Firmware Architecture | Define firmware stack and power management logic. | Firmware Design Document | Firmware Team |
| Week 4 | Schematic Design | Develop complete circuit schematic. | Schematic Document | Hardware Team |
| Week 5 | PCB Layout Design | 4‑layer PCB design with EMI optimization. | PCB Layout Files | Hardware Team |
| Week 6 | Latch/Switch Integration | Integrate magnetic/IMU wake‑sleep circuit. | Schematic + PCB Files | Hardware Team |
Phase 2 – Prototype Development and Lab Testing (8 Weeks)
| Week | Task | Description | Deliverable (Internal) | Responsibility |
|---|---|---|---|---|
| Week 7 | Component Procurement | Order and receive selected components. | Stocked Components | Procurement Team |
| Week 8–9 | PCB Fabrication – Batch 1 | Manufacture 5 prototype units. | 5 Assembled Units | Production Team |
| Week 10 | PCB Assembly – Batch 1 | Assemble PCBs. | Assembled PCBs | Hardware Team |
| Week 11–12 | Bring‑Up & Initial Testing | Power‑on, sensor, communication bring‑up. | Initial Bring‑Up Report | Hardware Team |
| Week 13–14 | Firmware Development Cycle 1 | Develop base firmware (LoRa Mesh, power, OTA). | Test Firmware Build | Firmware Team |
| Week 15 | Functional Testing – Batch 1 | Accuracy, signal, power, wake‑sleep tests. | Functional Test Report | Hardware + Firmware Team |
Phase 3 – Internal and Field Testing (8 Weeks)
| Week | Task | Description | Deliverable (Internal) | Responsibility |
|---|---|---|---|---|
| Week 16–17 | PCB Fabrication – Batch 2 | Manufacture 20 units for pilot testing. | 20 Assembled Units | Hardware Supplier |
| Week 18 | Internal Lab Testing | Environmental, robustness, signal strength validation. | Internal Test Report | Firmware + Hardware Team |
| Week 19–20 | Firmware Development Cycle 2 | Refine stability, OTA, encryption. | Updated Firmware Build | Firmware Team |
| Week 21 | Field Setup – Batch 2 | Deploy pilot units. | Deployment Report | Deployment Team |
| Week 22 | Performance Testing | Detect accuracy, false positives/negatives, RF quality. | Field Test Report | Firmware Team |
| Week 23 | Battery Performance Validation | Long‑duration battery tests. | Battery Test Report | Hardware + Firmware Team |
| Week 24 | Field Testing – Batch 3 | Final extended evaluation. | Final Test Report | Deployment Team |
Phase 4 – Pre‑Certification & Handover (2 Weeks)
| Week | Task | Description | Deliverable (Internal) | Responsibility |
|---|---|---|---|---|
| Week 25 | Performance Issue Resolution | Fix issues and finalize improvements. | Resolution Log | Hardware + Firmware Team |
| Week 26 | Certification Readiness & Handover | Prepare CE/FCC documents, final handover. | Certification Package | Technical Architecture Team |