Time Lines

Phase 1 – Requirement Finalization & System Design (3 Weeks)

WeekTaskDescriptionDeliverable (Internal)Responsibility
Week 1Requirement FinalizationFinalize system requirements including wagon counting accuracy, load profiling logic, speed/ETA calculation, train ID association, deployment constraints, and site inputs.Final Requirement DocumentHardware + Firmware Team
Week 2Component Selection & Architecture FinalizationFinalize selection of 3D LiDAR, distance LiDAR, AI LPR camera, edge controller, Wi-Fi modules, and overall system architecture.Approved BoMHardware Team
Week 3Schematic & Firmware Architecture DesignComplete hardware schematics and define firmware architecture for multi-sensor acquisition, synchronization, and data correlation.Schematic + Firmware Design DocumentHardware + Firmware Team

Phase 2 – Prototype Development & Firmware Implementation (5 Weeks)

WeekTaskDescriptionDeliverable (Internal)Responsibility
Week 4PCB Layout & Design Finalization4-layer PCB layout optimized for LiDAR interfaces, EMI/ESD protection, and outdoor operation.PCB Layout FilesHardware Team
Week 5Component ProcurementProcurement of approved sensors, camera units, edge controller components, and networking hardware.Stocked ComponentsProcurement Team
Week 6PCB Fabrication & Assembly – Batch 1Manufacture and assemble first batch of prototype edge controller units.Assembled UnitsProduction Team
Week 7Bring-Up & Hardware ValidationPower-on validation, LiDAR bring-up, camera triggering, and Wi-Fi connectivity testing.Initial Bring-Up ReportHardware Team
Week 8Firmware Development – Core FeaturesImplementation of sensor data capture, wagon segmentation logic, speed detection, and data upload.Test Firmware BuildFirmware Team

Phase 3 – Integration, Testing & Field Deployment (4 Weeks)

WeekTaskDescriptionDeliverable (Internal)Responsibility
Week 9System Integration & Functional TestingIntegrated validation of wagon counting, load detection, sensor synchronization, and data integrity.Functional Test ReportHardware + Firmware Team
Week 10Internal Lab & Environmental TestingEnvironmental, vibration, dust, and continuous operation testing under simulated rail conditions.Internal Test ReportFirmware + Hardware Team
Week 11Field Installation & CalibrationTrackside installation, sensor alignment, calibration, and commissioning.Deployment ReportDeployment Team
Week 12Field Performance ValidationValidation of wagon count accuracy, load classification, speed/ETA accuracy, and network reliability.Field Test ReportFirmware Team

Phase 4 – Optimization & Handover (2 Weeks)

WeekTaskDescriptionDeliverable (Internal)Responsibility
Week 13Performance Optimization & Issue ResolutionResolution of field-identified issues, algorithm tuning, and stability improvements.Resolution LogHardware + Firmware Team
Week 14Documentation, Pre‑Compliance & HandoverPreparation of CE pre-compliance documents, system documentation, and formal handover.Certification PackageTechnical Architecture Team